Multiple road closures occurring during the daylight hours of 8:00 A.M. through 2:00 P.M. are scheduled for culvert projects on the following dates and locations:

On April 12, 2021 replacing culvert along county road 102, Mt. Olivett Road, 0.1 miles south of the township road 178, Fairview Street, intersection.

On April 13, 2021 replacing culvert along county road 124, Wright Road, 0.03 miles southwest of the township road 153, Hall Boston Road, intersection.

On April 14, 2021 concreting culvert crossing along county road 26, Twenty Six Road, 0.06 miles south of the township road 71, Fitzgerald Road, intersection.

On April 15, 2021 concreting culvert crossing along county road 26, Twenty Six Road, 0.16 miles northeast of the state road 148, West Captina Highway, intersection.

The projects are weather dependent. Advance warning signs will be posted.